1、 西南交通大学本科毕业设计(论文) 第 14 页 Urban Underground Railroad arch tunnel Construction Technology Group Abstract Project in Guangzhou Metro Line, right-arch construction method of tunnels to explore. Subway Construction in Guangzhou for the first time put forward a double-arch tunnel to single-hole tunnel con
2、struction technology, and a single type of wall and split in the wall structure, comparison and selection of Technology solutions were obtained to meet the structural safety, construction safety and Economic benefits of better Technology solutions for the future design and construction of similar pr
3、ojects to provide reference and reference. Keywords: double-arch tunnel group; a single type of wall; construction Technology; split in the wall. As the circuit design requirements subway tunnel, the tunnel structure produces a variety of forms, ranging from cross-section from double-arch and the th
4、ree-arch tunnel composed of double-arch tunnel section is commonly used in the connection lines and crossing lines. In this paper, engineering examples, according to tunnel in which geological conditions, duration requirements, raised through the comparison and selection can achieve rapid constructi
5、on and the purpose of construction cost savings of the best construction programs. 1 Project OverviewGuangzhou Metro Line Road station turn-back line of sports for sports Road station after the return line, structure complex, DK3 016.047 037.157 varying cross-section set the double-arch structure, t
6、hree-arch structure of tunnels. Ranging from cross-arch tunnel excavation span 20.1m, excavation height of 10.076m, cross-vector ratio of 1:0.5, after lining a hole span 5.2m, large holes, after lining span 11.4m, the wall thickness of 1.6 m. Three double-arch tunnel excavation span 19.9m, excavatio
7、n height of 7.885m, cross-vector ratio of 1:0.1. -Arch tunnel section of rock from top to bottom are: artificial fill soil, red - alluvial sand, alluvial - alluvial soil, river and lake facies soil, plastic-like residual soil, hard plastic - a hard-like residual soil, all weathered rock, strong weat
8、hering rock, the weathered layer and the breeze layer. Tunnel through the rock strata are more homogeneous, the intensity high, carrying ability, good stability. Thickness of the tunnel vault covering 15.5 18m, of which grade Wai rock vault thickness 5.6 7.6m. Double-arch tunnel segment groundwater
9、table is 2.28 4.1m, mainly Quaternary pore water and fissure water. Section 2 dual-arch construction scheme comparisonAs the double-arch tunnel segment structure more complex, the tunnel cross-section changes in large, complicated construction process, construction was very difficult, the constructi
10、on cycle is long, so I chose a good quality and efficient completion of the construction program segment arch tunnel construction is particularly important. Selection of a construction program, the main consideration the following aspects: (1) construction safety and structural safety; (2) construct
11、ion difficulties; (3) the construction cycle; (4) cost-effectiveness. Based on these four principles, through the construction of research and demonstration program to select the following two programs to compare the selection of the construction.2.1 a single type of wall construction plan The progr
12、ams main construction steps and measures are as follows: (1) The right line of double-arch tunnel hole within the return line side of temporary construction access, dual-arch and the three-arch in the wall construction, is completed in a timely support for the wall, the construction to prevent bias.
13、 (2) construction of the wall lining is completed, according to first small then big, closed into a ring principle, the right line with the step method of construction, with CRD engineering method returned a four-lane span tunnel construction. (3) When the return line side of the construction to the
14、 three-arch tunnel in the wall, then in accordance with the right line of the wall construction method and the three-arch-arch in the wall construction, during which the right line to stop excavation until the completion of construction of the wall. (4) The return line side of the wall construction
15、is completed, the right line to continue to move forward the construction. The construction method for the domestic double-arch tunnel of conventional construction method, Guangzhou Metro, Nanjing and Beijing Metro subway both applications, and can secure successful completion of the construction of
16、 tunnels. However, examples of past engineering and construction Technology research can be found, the program has weaknesses and shortcomings. (1) The program used in this project, in a short span of 21.11m of double-arch tunnel, the tunnels opening between the supporting and secondary lining will
17、be converted four times, the conversion too frequently. (2) wall and side holes covered by waterproof layer of tunnel lining construction, steel engineering, formwork, concrete pouring required multiple conversions, the construction period up to 2 months. (3) The lining is completed, the wall of ant
18、i-bias materials, equipment, support and input, resulting in higher construction costs, Economic efficiency will drop. 2.2 The split in the wall construction plan The programs main construction steps and measures are as follows: (1) ranging from cross-double-arch tunnel into two single-hole, change
19、the formula for the separation wall, the first line of one-way right-forward construction of the tunnel. (2) three arch tunnel in the wall to make the first non-Shi lining, according to single-line working condition through. (3) the right line of large-section double-arch tunnel wall construction me
20、thod adopted in accordance with CRD. (4) The return line is in accordance with the right line of the opposite side of the construction sequence of construction. Adoption of this program is in fact a one-way in accordance with the construction of two methods, compared with the previous one, after the
21、 program has the following advantages:(1) reduction of the construction process to speed up the convergence process conversion. (2) reduce the construction difficulty, shortening the construction cycle. (3) reduce the construction costs and improve Economic efficiency. (4) change a single type of wa
22、ll to separate the wall, completely solved the structure of double-arch tunnel waterproofing defects. (5) The three-arch tunnel in the latter pArt of the construction hole, equivalent to large-span rock tunnels reserved for the core is conducive to both sides of the double-arch tunnel construction s
23、afety (Table 1). Section 3 three-arch construction plan Right-line direct access to three double-arch tunnel, the Support parameters to the original designs for grating erection of the whole ring, according to design the whole ring of shotcrete, and enhance the bolt at the wall vault settings (retur
24、n right side Tong Line Construction method), wall construction in the tunnel when you need to get rid of Office, located at a vertical grill joints strengthened beam. Strict control of excavation footage of each cycle, grid spacing of 0.6m / Pin. Weak in the wall excavation using millisecond blastin
- 1.请仔细阅读文档,确保文档完整性,对于不预览、不比对内容而直接下载带来的问题本站不予受理。
- 2.下载的文档,不会出现我们的网址水印。
- 3、该文档所得收入(下载+内容+预览)归上传者、原创作者;如果您是本文档原作者,请点此认领!既往收益都归您。
下载文档到电脑,查找使用更方便
免费下载 | 加入VIP,下载更划算! |
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- 城市 地下铁道 隧道 施工 技术研究 英文翻译