1、外文文献及翻译Project Budget Monitor and ControlAuthor:Yin Guo-liNationality:AmericanDerivation: Management Science and Engineering. Montreal: Mar 20, 2010.With the marketing competitiveness growing, it is more and more critical in budget control of each project. This paper discusses that in the constructi
2、on phase, how can a project manager be successful in budget control. There are many methods discussed in this paper, it reveals that to be successful, the project manager must concern all this methods.1. INTRODUCTIONThe survey shows that most projects encounter cost over-runs (Williams Ackermann, Ed
3、en, 2002,pl92). According to Wright (1997)s research, a good rule of thumb is to add a minimum of 50% to the first estimate of the budget (Gardiner and Stewart, 1998, p251). It indicates that project is very complex and full of challenge. Many unexpected issues will lead the project cost over-runs.
4、Therefore, many technologies and methods are developed for successful monitoring and control to lead the project to success. In this article, we will discuss in the construction phase, how can a project manager to be successful budget control. 2. THE CONCEPT AND THE PURPOSE OF PROJECT CONTROL AND MO
5、NITORErel and Raz (2000) state that the project control cycle consists of measuring the status of the project, comparing to the plan, analysis of the deviations, and implementing any appropriate corrective actions. When a project reach the construction phase, monitor and control is critical to deliv
6、er the project success. Project monitoring exists to establish the need to take corrective action, whilst there is still time to take action. Through monitoring the activities, the project team can analyze the deviations and decide what to do and actually do it. The purpose of monitor and control is
7、 to support the implementation of corrective actions, ensure projects stay on target or get project back on target once it has gone off target。3. SETTING UP AN EFFICIENT CONTROL SYSTEMFor the purpose of achieving cost target, the manager need to set up an efficient management framework including: re
8、porting structure, assessing progress, and communication system. The employees responsibility and authority need to be defined in the reporting structure. The formal and informal assessing progress can help getting a general perspective between reality and target. It is significant to help identify
9、what is the risk and should be monitored and controlled. Project success is strongly linked to communication. The efficient communication system benefit for teamwork and facilitate problem solving ( Diallo and Thuillier, 2005 ).4. COST MONITOR AND CONTROL4.1 Ranking the priority of monitoringIn cons
10、truction phase, many activities are carried out based on the original plan. It is need to know what kind of activities or things are most likely to lead the project delay and disruption. Therefore, the first step is ranking the priority of the activities. Because the duration of a project is determi
11、ned by the total time of activities on critical path, any delay in an activity on the critical path will cause a delay in the completion date for the project (Ackermann Eden, Howick and Williams,2000,p295). Therefore, the activities on critical path should firstly to be monitored and controlled. Sec
12、ondly, monitoring the activities with no free float remaining, a delay in any activity with no free float will delay some subsequent activity inevitably. These subsequent delays will discomfit the resource schedule significantly. Some resources are unavailable because they are committed elsewhere. T
13、hirdly, monitoring the activities with less than a specified float, because if an activity has very little float, it might use up the time before control decision is made once such an activities has a variance with the target. Fourthly, managers should monitor high risky activities. High risky activ
14、ities are most likely to overspend. Fifthly, managers should monitor the activities using critical resource. Some resource is critical because they are very expensive or limited (Cotterell and Hughes, 1995).4.2Methods of cost controlThe main cost of a project includes staff cost, material cost and d
15、elay cost. To control these cost, managers should first set up a cost control system to:a) Allocate responsibilities for administration and analysis of financial datab) Ensure all costs are properly allocated against project codesc) Ensure all costs are genuinely in pursuit of project activitiesd) C
- 1.请仔细阅读文档,确保文档完整性,对于不预览、不比对内容而直接下载带来的问题本站不予受理。
- 2.下载的文档,不会出现我们的网址水印。
- 3、该文档所得收入(下载+内容+预览)归上传者、原创作者;如果您是本文档原作者,请点此认领!既往收益都归您。
下载文档到电脑,查找使用更方便
20 积分
下载 | 加入VIP,下载更划算! |
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- 成本 管理 外文 文献 翻译