项目风险管理分析中英文对照外文翻译文献.doc
《项目风险管理分析中英文对照外文翻译文献.doc》由会员分享,可在线阅读,更多相关《项目风险管理分析中英文对照外文翻译文献.doc(15页珍藏版)》请在沃文网上搜索。
1、河北科技师范学院2013届本科毕业论文(设计)外文翻译Project Risk AnalysisChapter 1 Introduction1.1 About this compendium This course compendium is to be used in the course “Risikostyring is projector”. The focus will be on the following topics: Risk identification Risk structuring Risk modeling in the light of a time schedu
2、le and a cost model Risk follows up We will also discuss elements related to decision analysis where risk is involved, and use of life cycle cost and life cycle profit models. The course compendium comprises a large number of exercises, and it is recommended to do most of the exercises in order to g
3、et a good understanding of the topics and methods described. A separate MS Excel program, pRisk.xls has been developed in order to assist numerical calculations and to conduct Monte Carlo simulation.1.2 DefinitionsAleatory uncertainty Variation of quantities in a population. We sometimes use the wor
4、d variability rather than aleatory uncertainty.Epistemic uncertainty Lack of knowledge about the “world”, and observable quantities in particular.Dependency The relation between the sequences of the activities in a project.Observable quantity A quantity expressing a state of the “world”, i.e. a quan
5、tity of the physical reality or nature, that is unknown at the time of the analysis but will, if the system being analyzed is actually implemented, take some value in the future, and possibly become known.Parameter We use the term parameter in two ways in this report. The main use of a parameter is
6、that it is a quantity that is a part of the risk analysis models, and for which we assign numerical values. The more academic definition of a parameter used in a probability1616statement about an observable quantity, X, is that a parameter is a construct where the value of the parameter is the limit
7、ing value where we are not able to saturate our understanding about the observable quantity X whatsoever new information we could get hold of.Parameter estimate The numeric value we assess to a parameter.Probability A measure of uncertainty of an event.Risk Risk is defined as the answer to the three
8、 questions 14: i) what can go wrong? ii) How likely is it? And if it goes wrong, iii) what are the consequences? To describe the risk is a scenario Risk acceptance A decision to accept a risk.Risk acceptance criterion A reference by which risk is assessed to be acceptable or unacceptable.Schedule A
9、plan which specifies the start and finalization point of times for the activities in a project.Stochastic dependency Two or more stochastic variables are (stochastically) dependent if the expectation of one stochastic variable depends on the value of one or more of the other stochastic variables.Sto
10、chastic variable A stochastic variable, or random quantity, is a quantity for which we do not know the value it will take. However, we could state statistical properties of the variable or make probability statement about the value of the quantity.1.3 DEFINITIONS Uncertainty Lack of knowledge about
11、the performance of a system, and observable quantities in particular.Chapter 2Risk Management Generally, risk management is defined (IEC 60300-3-9) as a “systematic application of management policies, procedures and practices to the tasks of analyzing, evaluating and controlling risk”. It will compr
12、ise (IEC definitions in parentheses): Risk assessment, i.e. Risk analysis (“Systematic use of available information to identify hazards and to estimate the risk to individuals or populations, property or the environment”) Risk evaluation (“Process in which judgments are made on the tolerability of t
13、he risk on the basis of risk analysis and taking into account factors such as socio-economic and environmental aspects”) Risk reduction/control (Decision making, implementation and risk monitoring).There exists no common definition of risk, but for instance IEC 60300-3-9 defines risk as a “combinati
14、on of the frequency, or probability, of occurrence and the consequence of a specified hazardous events”. Most definitions comprise the elements of probabilities and consequences. However, some as Klinke and Renn suggest a very wide definition, stating: “Risk refers to the possibility that human acti
15、ons or events lead to consequences that affect aspects of what humans value”. So the total risk comprises the possibility of number (“all”) unwanted/hazardous events. It is part of the risk analysis to delimit which hazards to include. Further, risk usually refers to threats in the future, involving
16、 a (high) degree of uncertainty. In the following we will present the basic elements of risk management as it is proposed to be an integral part of project management.2.1 Project objectives and criteria In classical risk analysis of industrial systems the use of so-called risk acceptance criteria ha
17、s played a central role in the last two or tree decades. Basically use of risk acceptance criteria means that some severe consequences are defined, e.g. accident with fatalities. Then we try to set an upper limit for the probability of these consequences that could be accepted, i.e. we could not acc
18、ept higher probabilities in any situations. Further these probabilities could only be accepted if risk reduction is not possible, or the cost of risk reduction is very high.In recent years it has been a discussion in the risk analysis society whether it is fruitful or not to use risk acceptance crit
19、eria according to the principles above. It is argued that very often risk acceptance criteria are set arbitrary, and these do not necessarily support the overall best solutions. Therefore, it could be more fruitful to use some kind of risk evaluation criteria, rather than strict acceptance criteria.
20、 In project risk management we could establish acceptance criteria related to two types of events: Events with severe consequences related to health, environment and safety. Events with severe consequences related to project costs, project quality, project duration, or even termination of the projec
21、t. In this course we will have main focus on the project costs and the duration of the project. Note that both project cost and project duration are stochastic variables and not events. Thus it is not possible to establish acceptance criteria to project cost or duration directly. Basically, there ar
22、e three types of numeric values we could introducein relation to such stochastic variables describing the project:1. Target. The target expresses our ambitions in the project. The target shall be something we are striving at, and it should be possible to reach the target. It is possible to introduce
23、 (internal) bonuses, or other rewards in order to reach the targets in a project.2. Expectation. The expectations are the value the stochastic variables will achieve in the long run, or our expectation about the outcome. The expectation is less ambitious than the target. The expectation will in a re
24、alistic way account for hazards, and threats and conditions which often contribute to the fact that the targets are not met.3. Commitment. The commitments are values related to the stochastic variables which are regulated in agreements and contracts. For example it could be stated in the contract th
- 1.请仔细阅读文档,确保文档完整性,对于不预览、不比对内容而直接下载带来的问题本站不予受理。
- 2.下载的文档,不会出现我们的网址水印。
- 3、该文档所得收入(下载+内容+预览)归上传者、原创作者;如果您是本文档原作者,请点此认领!既往收益都归您。
下载文档到电脑,查找使用更方便
10 积分
下载 | 加入VIP,下载更划算! |
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- 项目风险 管理 分析 中英文 对照 外文 翻译 文献