建筑工程中英文翻译(适用于毕业论文外文翻译+中英文对照).docx
《建筑工程中英文翻译(适用于毕业论文外文翻译+中英文对照).docx》由会员分享,可在线阅读,更多相关《建筑工程中英文翻译(适用于毕业论文外文翻译+中英文对照).docx(13页珍藏版)》请在沃文网上搜索。
1、 Construction Engineering Construction engineering is a specialized branch of civil engineering concerned with the planning, execution, and control of construction operations for such projects as highways, buildings, dams, airports, and utility lines. Planning consists of scheduling the work to be d
2、one and selecting the most suitable construction methods and equipment for the project. Execution requires the timely mobilization of all drawings, layouts, and materials on the job to prevent delays to the work. Control consists of analyzing progress and cost to ensure that the project will be done
3、 on schedule and within the estimated cost. Planning. The planning phase starts with a detailed study of construction plans and specifications. From this study a list of all items of work is prepared, and related items are then grouped together for listing on a master schedule. A sequence of constru
4、ction and the time to be allotted for each item is then indicated. The method of operation and the equipment to be used for the individual work items are selected to satisfy the schedule and the character of the project at the lowest possible cost. The amount of time allotted for a certain operation
5、 and the selection of methods of operation and equipment that is readily available to the contractor. After the master or general construction schedule has been drawn up, subsidiary detailed schedules or forecasts are prepared from the master schedule. These include individual schedules for procurem
6、ent of material, equipment, and labor, as well as forecasts of cost and income. Execution. The speedy execution of the project requires the ready supply of all materials, equipment, and labor when needed. The construction engineer is generally responsible for initiating the purchase of most construc
7、tion materials and expediting their delivery to the project. Some materials, such as structural steel and mechanical equipment, require partial or complete fabrication by a supplier. For these fabricated materials the engineer must prepare or check all fabrication drawings for accuracy and case of a
8、ssembly and often inspect the suppliers fabrication. Other construction engineering duties are the layout of the work by surveying methods, the preparation of detail drawings to clarify the design engineers drawings for the construction crews, and the inspection of the work to ensure that it complie
9、s with plans and specifications. On most large projects it is necessary to design and prepare construction drawings for temporary construction facilities, such as drainage structures, access roads, office and storage buildings, formwork, and cofferdams. Other problems are the selection of electrical
10、 and mechanical equipment and the design of structural features for concrete material processing and mixing plants and for compressed air, water, and electrical distribution systems. Control. Progress control is obtained by comparing actual performance on the work against the desired performance set
11、 up on the master or detailed schedules. Since delay on one feature of the project could easily affect the entire job, it is often necessary to add equipment or crews to speed up the work. Cost control is obtained by comparing actual unit costs for individual work items against estimated or budgeted
12、 unit costs, which are set up at the beginning of the work. A unit cost is obtained by dividing the total cost of an operation by the number of units in that operation. Typical units are cubic yards for excavation or concrete work and tons for structural steel. The actual unit cost for any item at a
13、ny time is obtained by dividing the accumulated costs charged to that item by the accumulated units of work performed Individual work item costs are obtained by periodically distributing job costs, such as payroll and invoices to the various work item accounts. Payroll and equipment rental charges a
14、re distributed with the aid of time cards prepared by crew foremen. The cards indicate the time spent by the job crews and equipment on the different elements of the work. The allocation of material costs is based on the quantity of each type of material used for each specific item. When the compari
15、son of actual and estimated unit costs indicates an overrun; an analysis is made to pinpoint the cause. If the overrun is in equipment costs, it may be that the equipment has insufficient capacity or that it is not working properly. If the overrun is in labor costs, it may be that the crews have too
16、 many men, lack of proper supervision, or are being delayed for lack of materials or layout. In such cases time studies are invaluable in analyzing productivity. Construction operations are generally classified according to specialized fields. These include preparation of the project site, earthmovi
17、ng, foundation treatment, steel erection, concrete placement, asphalt paving, and electrical and mechanical installations. Procedures for each of these fields are generally the same, even when applied to different projects, such as buildings, dams, or airports. However, the relative importance of ea
18、ch field is not the same in all cases. Preparation of site. This consists of the removal and clearing of all surface structures and growth from the site of the proposed structure. A bulldozer is used for small structures and trees. Larger structures must be dismantled. Earthmoving. This includes exc
19、avation and the placement of earth fill. Excavation follows preparation of the site, and is performed when the existing grade must be brought down to a new elevation. Excavation generally starts with the separate stripping of the organic topsoil, which is later reused for landscaping around the new
20、structure. This also prevents contamination of the nonorganic material which is below the topsoil and which may be required for fill. Excavation may be done by any of several excavators, such as shovels, draglines, clamshells, cranes, and scrapers. Efficient excavation on land requires a dry excavat
21、ion area, because many soils are unstable when wet and cannot support excavating and hauling equipment. Dewatering becomes a major operation when the excavation lies below the natural water table and intercepts the groundwater flow. When this occurs, dewatering and stabilizing of the soil may be acc
22、omplished by trenches, which conduct seepage to a sump from which the water is pumped out. Dewatering and stabilizing of the soil may in other cases be accomplished by wellpoints and electroosmosis. Some materials, such as rock, cemented gravels, and hard clays, require blasting to loosen or fragmen
23、t the material. Blast holes are drilled in the material; explosives are then placed in the blast holes and detonated. The quantity of explosives and the blast-hole spacing are dependent upon the type and structure of the rock and the diameter and depth of the blast holes. After placement .of the ear
24、th fill, it is almost always compacted to prevent subsequent settlement. Compaction is generally done with sheeps-foot, grid, pneumatic-tired, and vibratory-type rollers, which are towed by tractors over the fillas it is being placed. Hand-held, gasoline-driven rammers are used for compaction close
- 1.请仔细阅读文档,确保文档完整性,对于不预览、不比对内容而直接下载带来的问题本站不予受理。
- 2.下载的文档,不会出现我们的网址水印。
- 3、该文档所得收入(下载+内容+预览)归上传者、原创作者;如果您是本文档原作者,请点此认领!既往收益都归您。
下载文档到电脑,查找使用更方便
20 积分
下载 | 加入VIP,下载更划算! |
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- 建筑工程 中英文 翻译 适用于 毕业论文 外文 对照